file it at that time. This request for extension of time was denied by the contracting officer on December 1, 1964, and on that same day he made his findings and determinations. In essence, he found as follows:
• The “Pinal Determination claim” filed by plaintiff on January 17, 1964, was not acceptable as a termination settlement proposal, because such claim was not set forth on the prescribed forms, was not signed, and was not certified.
• The final settlement proposal of March 31, 1954, was the most recent settlement proposal in proper form.
• Plaintiff was entitled to a total settlement of $219,154.98. Deducting the $200,000 previously paid on account, this left a balance due plaintiff in the sum of $19,154.98.
Plaintiff appealed the contracting officer’s decision to the Armed Services Board of Contract Appeals (ASBCA) on December 30, 1964. On appeal, the Board took into consideration plaintiff’s March 31, 1954, settlement proposal, plaintiff’s January 17, 1964 “Final Determination Claim,” the contracting officer’s decision, and the testimony and the briefs of the parties.
The Board decision, 66-2 BCA ff 5731, ASBCA No. 10534, dated August 1, 1966, increased plaintiff’s amount of recovery from the $219,154.98 figure granted by the contracting officer to a total figure of $479,264.01. The follow-lowing table shows the itemized amounts, and compares the amounts granted by the contracting officer and the Board:
Item C/O Decision Board Difference
Metals -------------------- $65,611.81 $74,825.10 +$9,213.29
Purchased Parts ---------- 9,489.40 9,489.40 ---------------
Work in Process ---------- 8,629.44 10,600.76 +1,971.32
Dies, Labor, Overhead 81,602.12 252,355.72 +170,753.60
Total Cost of Sales-------- $165,332.77 $347,270.98 +$181,938.21
G & A-------------------- 21,708.19 56,466.26 +34,758.07
Profit ------------------- 10,457.20 24,224.23 +13,767.03
Settlement Exp ---------- 9,544.04 39,189.76 +29,645.72
Settlements With
Subcontractors---------- 9,930.78 9,930.78 _______________
Acceptable Finished
Product----------------- 2,182.00 2,182.00 ---------------
Total Settlement — $219,154.98 $479,264.01 $260,109.03
Subtracting the $200,000 paid on account in 1953 from the $479,264.01 allowed by the Board resulted in a net amount due plaintiff in the sum of $279,264.01.
Plaintiff’s financial problems, however, were still far from being over. In October 1960, thé Internal Revenue Service had notified the commanding officer of the DOD that plaintiff was indebted to the United States for Federal taxes, penalty and interest, and requested that any funds due the plaintiff be forwarded to the IRS to be applied on the tax indebtedness. The Department of the Army issued a directive stating that no contract funds were to be disbursed to plaintiff until its tax in