hereunder to be timely and properly performed.
(A237, 420.)
B. Procedural History
ACA commenced this action by filing a complaint against C & B on June 27, 2005. ACA later filed four amended complaints, all of which asserted claims against C & B for both breach of contract and professional negligence.
On March 26, 2008, C & B moved for partial summary judgment, seeking a ruling that it was not liable for (1) consequential damages, in light of Section F, Paragraph 4 of the Proposal and Paragraph 1.3.6 of the Agreements, or (2) damages in excess of its compensation, in light of Section F, Paragraph 1 of the Proposal. On November 13, 2008, the District Court issued an opinion that (1) declined to issue guidance as to what types of damages were consequential, and (2) held that because the limitation on damages in excess of compensation in Section F, Paragraph 4 conflicted with Paragraph 2.9.2.2 of the Agreements, it was not incorporated into the Agreements.
On April 13, 2009, C & B filed a motion in limine to bar ACA from introducing evidence of consequential damages relating to loss of use, loss of profit, and claims for delay, impact or disruption. On June 18, 2009, the District Court denied this motion in substantial part.
Following a thirteen-day trial, the jury returned a verdict on July 7, 2009, awarding ACA the following damages:
$1,307,073.00 Additional construction costs to fix errors
$3,617,442.00 Lost rental income
$1,688,048.30 Additional payments to contractors due to delay
$ 996,231.00 Additional administrative costs
(A24-27.) These damages were awarded on both the negligence and contract claims.
On March 31, 2010, the District Court denied C & B’s motions for judgment as a matter of law or for a new trial. In a separate order, it granted ACA’s motion for attorneys’ fees, costs, and pre-judgment interest — fees in the amount of $2,491,373.50; costs in the amount of $949,311.31; and pre-judgment interest in the amount of $1,653,088.71. These additions brought ACA’s total recovery to $12,702,567.82.
II. Discussion
A. Jurisdiction and Standard of Review
The District Court exercised subject matter jurisdiction pursuant to 28 U.S.C. § 1332, and we have appellate jurisdiction pursuant to 28 U.S.C. § 1291. The correct interpretation of a contract is a question of law that we review de novo. United States v. Hardwick, 544 F.3d 565, 570 (3d Cir.2008).
B. Availability of Consequential Damages
C & B’s primary argument is that the District Court erred by allowing ACA to recover consequential damages, which it defines to include $3,617,442.00 of lost rental income, $1,688,048.30 for additional payments to contractors due to delay, and $996,231.00 of additional administrative costs. We agree. Although the District Court correctly determined that C & B was not liable for ACA’s consequential damages, its analysis of what damages were consequential was erroneous.
The essence of the District Court’s determination was that Paragraph 2.9.2.3 of the Agreements contained an express promise not to delay the project and that any damages following foreseeably from a