it must take the consequences. It could not ask the court to declare that it owed only so much to Ondrick, and that the court should discharge it from his claim for extra work, and then, when Ondrick resisted such a declaration, demand that Ondrick arbitrate.
Next, Ferber asserts that a series of so-called releases executed from time to time by Ondrick in connection with progress payments bars recovery. These documents do not use the word “release” in the title, nor is it in the body of the instrument except with respect to liens upon the premises. Ondrick is not presently asserting liens. The documents were prepared by Ferber and are to be construed against it. We agree with the court in disregarding them.
We come, therefore, to the merits. The principal contract called for the erection of ninety-six structures, all of which were to have concrete cellars, with drainage fill under the concrete. By the end of September 1958 some of the foundations were ready for the fill. The principal contract required the fill to be placed and, in addition, to be “compacted.” Ferber took the position that all of this work was included in the subcontract and demanded that Ondrick do it. On-drick admitted responsibility for supplying the gravel at the locus, but denied any further obligation. On the evidence most favorable to Ondrick, one Cristello, Ferber’s superintendent, instructed Ondrick to place and compact the gravel, and stated that if this did not prove to be within the subcontract Ferber would pay extra for it. Ondrick thereafter did the filling and compacting for all ninety-six units, and presented a bill in the amount of |19,744.
The court found that installing the fill was not within the subcontract. This was a question of interpretation, and it is sufficient to say that we find the district court’s reasoning persuasive.2 The contract provided further, under the subtitle “Change Orders Additions and Deductions” that “alterations” should not be effected except by written order of Ferber. No written order was given for this extra work. The court, however, found that Cristello had sufficient authority to alter the contract.
It is, of course, rudimentary that a contractual requirement that agreements be in writing may be waived. Lord Constr. Co. v. United States ex rel. W. E. Sexton Co., 3 Cir., 1928, 28 F.2d 340; Zarthar v. Saliba, 1933, 282 Mass. 558, 185 N.E. 367. The fact, however, that Cristello may have possessed authority to waive a writing, and substantially to enlarge the agreement, is of little help to Ondrick so far as the total amount of the recovery here involved is concerned. On his own testimony the top officials of Ferber informed Ondrick at some point that this work was within his original contract and must be done thereunder. According to Ferber’s evidence this took place in December 1958. Ondrick testified that he was entirely unable to place the date, but he admitted that this work lasted until December 1959 and that many individual unit jobs were done by him after Ferber’s interview, as result of pressure put on him by the top Ferber officials acting through the bonding company, although he constantly maintained that he was not required to do it. It cannot be said that Cristello’s promise to pay extra if this was in fact extra work remained in effect for jobs undertaken after Ferber’s repudiation thereof. The court made no finding which would enable us to separate the amount, or value, of the work done before Ferber’s repudiation and afterwards.
The court, however, made an alternative finding or ruling with which we agree, namely, that Ondrick was entitled to recover on a quantum meruit for unjust enrichment. Normally a party doing work without a contract for another party who has stated in advance
2
We note, inter alia, that in order to support its construction Ferber is required to say that some of the language of the agreement is surplusage, a presumptively unsound position.