Fischers admitted their default, admitted Fireman’s right and duty to take over and complete the contracts, and admitted that Fireman’s had incurred a net loss of $555,928.97 in completing the work and paying the bills. The jury was further instructed, however, that the Fischers asserted that Fireman’s had “paid excessive prices for the completion of the contracts” and if the jury found any of Fireman’s expenditures were not reasonable, necessary or proper, they should reduce Fireman’s recovery accordingly. But the jury was also told that the burden was on the Fischers ' to prove this claim of excessive expenditures. Since we affirm the summary judgment and the judgment on the directed verdict, these instructions are the dimensions of our lawsuit. And if the jury understood and followed the court’s instructions, they apparently thought the completion expenditures were excessive, since the verdict was for only $200,000.
If we interpret the verdict as a finding that the net loss should have been $200,000 rather than the $555,928.-97 actually incurred, the question is whether the verdict is supported by the evidence. Otherwise stated, the question is whether the Fischers’ proof impugned the integrity of the admitted net loss, and, if so, to what extent.
The only countervailing evidence on the completion costs was the testimony of John and Raymond Fischer. John Fischer who admitted that he was concerned with the “field” aspects of the work and did not keep track of costs, testified that he estimated the labor costs in completing two of the contracts at from $15,000 to $18,000 and the cost of completing a third at from $2500 to $3000 a week' for 25 or 30 working days. This witness was admittedly unfamiliar with the projection of costs of construction and his calculations failed to take account of the costs other than labor incurred by the completing contractors and of the variables entering into the calculation of the labor cost itself. The contrast between the generality of his labor cost estimates and the completeness and specificity of Fireman’s actual completion costs emphasizes his statement’s lack of probative value. Indeed, we are unable to determine with any degree of accuracy what the total cost of completion would be under John Fischer’s calculations, and nothing in the briefing sheds any light on this theory of the case.8 For these reasons we cannot regard his testimony as in derogation of the reasonableness of Fireman’s completion costs, nor as in support of the verdict of the jury.
The issue thus turns on the probity of Raymond Fischer’s testimony. On the basis of his own cost accounting records, he testified that the value of work remaining to be completed in the contracts was $188,000 and that he and his brother could have completed the work for $87,000, resulting in a total loss of $30,000 after completion and paying all bills. The manner in which the $30,000 loss was calculated was never explained, nor was there any explanation of how work valued at $188,000 could be completed for $87,000. The briefing is also noticeably deficient in this respect. The $188,000 in work to be completed is likewise without a rational basis. Raymond Fischer obtained that figure by subtracting the amount earned on the contracts (plus the value of materials on the job sites) from the total bid price of the contracts. This calculation rested on the assumption that Fischers’ total bid price was equivalent to the actual cost of performance. The validity of this assumption is completely dissipated by the fact that he was unable to pay bills of $400,000 on the contracts to the time of Fireman’s intervention.
We do not think Raymond Fischer’s testimony provides any support for the $200,000 verdict, not do we think it de
8
The only support for the verdict offered by the Fischers’ brief was that the cost of completion should have been $35,000 rather than the $317,000 actually spent, reducing the net loss to approximately $218,000. This calculation was based on labor costs alone and failed to take account of the other obvious costs incurred under the completion contracts.