“patches” were present in the system’s programming materials. Notwithstanding these problems, the tests proceeded. Plaintiff’s program manager still felt that defendant’s requirements could be met. Difficulties developed in the system during the introduction of test messages and the tests were again terminated on February 19, 1968.
Plaintiff, by letter dated February 26, 1968, stated that the failure of the message test was not due to any fault on its párt and that most deficiencies in the system had been located or corrected. However, before this information reached the Government representatives, the contracting officer on February 26, 1968 terminated the contract for default for failure to deliver the system required by the contract.10 As of the termination date, nearly nine months after the original contractual delivery date, plaintiff had expended in excess of $700,000.
Plaintiff timely appealed from the final decision of the contracting officer terminating the contract for default. The Board on September 29, 1971 concluded that the termination for default was proper and denied plaintiff’s appeal. In its petition filed May 31, 1972, plaintiff brought this action under the general jurisdiction of this court, 28 U.S.C. § 1491 (1970), for review of the administrative decision under both sections of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1970).
UNILATERAL ESTABLISHMENT OF CONTRACT COMPLETION DATE
Plaintiff contends that the Board erred in finding February 19, 1968 had been established unilaterally as the new contract completion date. Defendant, on the other hand, argues that the Board’s determination should be accorded finality by this court.
We hold plaintiff’s position to be correct.
Even though the Board properly refused to find that February 9, 1968 ever became an enforceable contract delivery date, it nevertheless gratuitously concluded that February 19, 1968 was established as the new contract delivery date. It was the Board’s opinion that the Government’s letter of February 15, 1968 served as a unilateral notice establishing a point in time at which the contractor would be considered in default if the system failed to comply with the contract performance requirements.
The Board felt that, although plaintiff had declined to fill in the blanks of the February 15 letter, “the Government representatives in effect did so by informing appellant [plaintiff] that they would return for further testing on 19 February.”
According to the Board, the letter was not drafted as a contract amendment and was only bilateral with regard to the fact that the Government requested plaintiff to insert a February date for final acceptance tests. The Board also felt that plaintiff’s signature was intended only to represent acknowledgement of receipt and understanding of the contents, but not necessarily agreement.
While the Board concluded that the Government unilaterally established February 19, 1968 as the contract completion date in accordance with DeVito v. United States, 413 F.2d 1147, 188 Ct.Cl. 979 (1969), this conclusion is erroneous. Plaintiff correctly contends that the only action taken at the meeting of February 15, 1968, was the agreement that the Government would resume testing on February 19, 1968. It seems clear that the February 15 letter, containing blanks instead of specific dates, did not comply with DeVito.
Under the DeVito rule, in a waiver after breach situation, time may again become essential and the Government may regain the right to terminate a delinquent contractor for default, if (1) the Government unilaterally issues a notice under the contract’s Default clause establishing a reasonable but specific time for performance on pain of default termination, or (2) the parties bilaterally
10
Plaintiff first learned of the termination decision by telephone on February 23, 1968.