The defendant divided the contract, awarding the first 12 items to another contractor, and awarding the last three items covering machine bolts to the plaintiff. Notice of award to plaintiff was mailed on October 4, 1948.
The invitation to bid contained the following provision:
“The successful bidder will receive Notice of Award at the earliest possible date, and such Award will thereupon constitute a binding contract between the bidder and the Government without further action on the part of the bidder.” [Italics supplied.]
The notice of award provided:
“This contract, executed as of the above date of the acceptance of your Bid, comprises the following documents :
“(a) the Government’s Invitation for Bids,
“(d) the General Provisions, and “(e) the Government’s Award.
“No further contractual document is necessary for the consummation of this contract.”
The plaintiff discovered its error late on Friday afternoon, October 1, and on the first working day thereafter, Monday, October 4, 1948, plaintiff’s sales manager communicated with plaintiff’s representative in Philadelphia, who immediately telephoned the Aviation Supply Office of the Navy Department in Philadelphia, notifying that office of plaintiff’s error and that it desired to withdraw its bid. Later the same day the company wired the Supply Office that it was withdrawing its bid on Items 13, 14, and 15. The record does not show whether the notice of award was mailed before or after the telephone conversation in which plaintiff advised the defendant of its mistake and asked to withdraw its bid. It was received by plaintiff after the telegram of withdrawal had been sent.
On October 6, 1948, Lt.(jg.) W. H. Underwood, Jr., wrote plaintiff acknowledging its telegram and advising that the bid could not be withdrawn after the opening date, and that the award had been mailed to plaintiff on October 4, 1948.
The catalogs and lists of record show that machine bolts are a more expensive type of bolt than the stud bolts. There is no question but that a mistake was made and that plaintiff submitted its bid upon the belief that the invitation to bid was for stud bolts and overlooked the fact that the last part of the invitation was for the more expensive type of bolt.
A rather well-established rule of law seems to be that after bids have been opened the bidder cannot withdraw his bid unless he can prove that the desire to withdraw is due solely to an honest mistake and that no fraud is involved. United States v. Lipman, D.C., 122 F.Supp. 284, 287; Alta Electric and Mechanical Co., Inc., v. United States, 90 Ct.Cl. 466; Leitman v. United States, 60 F.Supp. 218, 104 Ct.Cl. 324; Nason Coal Co. v. United States, 64 Ct.Cl. 526; Moffett, Hodgkins & Clarke Co. v. City of Rochester, 178 U.S. 373, 20 S.Ct. 957, 44 L.Ed. 1108. The case of Refining Associates, Inc., v. United States, 124 Ct.Cl. 115, cited by both parties and emphasized by the defendant, is inapplicable to the facts of this case. No mistake was found to exist in that case. In fact, in that case the court recognized that on many occasions it has granted relief to plaintiffs seeking to withdraw or modify a bid after the date of the opening. It cites and discusses several such cases and distinguishes them from that particular case. In the instant case the plaintiff on account of its mistake had a right to withdraw its bid, provided a binding contract had not yet been made.
The question is whether, in all the circumstances of this case, the depositing of the notice of award in the mail constitutes a binding contract from which plaintiff cannot escape, notwithstanding the mistake was brought to the attention