which, when viewed together, have cumulatively significant impacts.” Vance v. Block, 635 F.Supp. at 168.
“Cumulative actions” are those “which when viewed with other proposed actions have cumulatively significant impacts.” 40 C.F.R. § 1508.25(a)(2) (1987). A cumulative impact is defined as:
the impact on the environment which results from the incremental impact of the actions when added to other past, present, and reasonably foreseeable future actions regardless of what agency ... or person undertakes such actions. Cumulative impacts can result from individually minor but collectively significant actions taking place over a period of time.
40 C.F.R. § 1508.7 (1987).
Both connected actions and unrelated, but reasonably foreseeable, future actions may result in cumulative impacts. As discussed, there is an inextricable nexus between the road reconstruction and the logging operations. Yet, the EA did not evaluate the environmental impacts of either the reconstruction or the ongoing and future accelerated timber harvest. The cumulative impact of these actions raises material issues of fact concerning the project’s effect upon the human environment. Thus, summary judgment was improper.
Ill
THE ENDANGERED SPECIES ACT
The appellants argue that the Forest Service failed to comply with the Endangered Species Act, 16 U.S.C. § 1531 et seq., because it did not prepare a biological assessment before it decided to proceed with the project, award a contract, and allow actual reconstruction to begin.
The appellees concede that the environmental assessment was untimely, but counter that: (1) the later BA cured the deficiency, (2) the appellants are barred by laches from contesting the adequacy of the EA, and (3) a failure to prepare the BA did not foreclose other reasonable alternatives. The district court held that the ESA cause of action was barred by laches.
The ESA, 16 U.S.C. § 1540(g)(1), provides for “citizens suits” to enforce the provisions of the Act. However, section 1540(g)(2)(A)(i) states that “[n]o action may be commenced under sub-paragraph (1)(A) of this section prior to sixty days after written notice of the violation has been given to the Secretary, and to any alleged violator of any such provision or regulation.” “Secretary” is defined to mean the Secretary of the Interior or the Secretary of Commerce. 16 U.S.C. § 1532(15).
This court recently held that a similar 60 day notice requirement in the Resources Conservation and Recovery Act of 1976, 42 U.S.C. § 6972(b)(1) was jurisdictional, not procedural. Hallstrom v. Tillamook County, 831 F.2d 889 (9th Cir.1987). Because the Hallstrom appellants failed to give written notice of the alleged violation to the Secretary before the 60 day period, Hallstrom held that the court lacked federal subject matter jurisdiction to reach the merits of the appellants’ claim. Id. at 891.
In this case, appellants rely on two letters, one written to Bill Morden, Supervisor of the Kootenai National Forest, Libby, Montana, and the other to Robert H. Shields, Regional Director, U.S. Fish and Wildlife Service, U.S. Dept, of Interior at the Denver Federal Center, Denver, Colorado, with carbon copies to various state and federal legislators and environmental groups, to satisfy the ESA’s written notice requirement. However, neither letter specifically gives notice of a violation or notice of an intention to sue. Even if these letters provided the requisite notice of a violation, the letters were not sent to the correct person, the secretary, as required. An actual notice of intention to sue was sent to the appellees by the appellants only 38 days before the appellants filed their complaint, and therefore cannot satisfy § 1540(g)(2)(A)(i)’s 60-day written notice requirement.
While this case involves a different environmental statute from the one at issue in Hallstrom, both statutes have very similar 60 day notice requirements. The only difference is that the ESA requires “written notice,” whereas the Resource Conservation Recovery Act requires only “notice”. Additionally, “courts have construed these [notice] provisions identically despite slight differences in wording.” Hallstrom, 831 F.2d at 890.
Because of the failure to give written notice timely, we lack jurisdiction to reach the ESA claim. Therefore, we dismiss the appeal with regard only to the ESA issue.