Rogosheske, Justice.
Plaintiff, upon dismissal of its action as to certain defendants, appeals from an order denying its motion for a new trial.
The problem presented concerns the interpretation of a building construction contract to ascertain the intention of the parties with respect to the contractor’s liability for alleged negligence in causing a fire which extensively damaged a school building after the construction was substantially completed and the budding was accepted and in use by plaintiff.
In the spring of 1956, plaintiff entered into a contract with Patch and Erickson, architects, relating to the construction of a new elementary school in the city of Buffalo, Minnesota. Under this contract, plans and specifications were drafted by Robert D. Hanson, an employee of Patch and Erickson. After approval of such plans by the school board of plaintiff, bids were solicited and accepted. Thereafter, in November 1956, pursuant to the contract with the architects, construction contracts incorporating the plans and specifications were similarly drafted and executed by the plaintiff and the successful bidders. Defendant Loberg Plumbing & Heating Company (hereinafter Loberg) contracted for the plumbing and heating work. Defendants Edward S. Kern and Frank Persons, doing business as The Kerntile Company, furnished the acoustical tile used in the construction as a subcontractor.
In September 1957, the building was occupied for school purposes although construction was not completed. On November 13, 1957, plaintiff, by its school board, inspected the new building and accepted it as completed, subject to “punch lists” of certain items which inspection revealed were to be corrected by various contractors, including Loberg, before final payment. On December 27, 1958, Lo-berg’s “punch list” items were certified as completed, and final payment was authorized and made to Loberg shortly after January 20,