When it became apparent that the original steel subcontractor would not be able to resume work, Newburgh sought to obtain plaintiffs services for the remainder of the project on a fixed-price basis. The parties agreed upon a contract price of $175,000, but evidently continued to disagree with respect to the scope of the work that was to be performed for that price. A written contract, dated April 3, 1991, was drafted by defendant Paul E. Tibby, Newburgh’s vice-president, but never executed by plaintiff.
Plaintiff periodically submitted invoices to Newburgh, with attached work order slips detailing the work for which payment was sought. Although Newburgh paid plaintiff amounts ranging between $5,000 and $15,000, on a more or less weekly basis throughout the spring and summer, the sums paid were, according to plaintiff’s proof, made “on account” and, as Tibby testified, bore no relation to the amount that had been billed; the payments were derived, the latter contended, by dividing the $175,000 contract price by the time estimated to complete the project. Tibby admitted that plaintiff had, at times, been paid less than had been invoiced, and at times more.
After each payment check was tendered, Newburgh had plaintiff execute a “Partial and Full Waiver of Liens”, displaying the date and amount of the payment, and containing a statement that the signer “acknowledges receipt of partial or full payment for work performed on, or materials supplied to” the project and “acknowledges that no other sums are now due and owing and waives and releases any claims which it may now or hereafter have upon the land and or buildings on this project”. Newburgh contends that each of these “waivers” constituted a full release of all claims arising from work performed prior to the date of the waiver. On each of these documents that appears in the record (with two exceptions, noted as clerical errors), however, James Walters, plaintiff’s president, had, prior to signing the form, crossed out the phrase “or full” in the first line quoted above. Walters testified that he made this modification to clarify that he was only acknowledging receipt of the amount of the particular check indicated, not full payment of all amounts due, and was merely releasing his right to file a lien as to the amount paid.
Plaintiff brought this action to recover an outstanding balance of approximately $205,000 it claims is still due and owing for work it performed on the project. After a nonjury trial, Supreme Court found that inasmuch as the parties had never had a meeting of the minds as to the scope of the work covered by the contract, no fixed-price agreement had been entered