matter, the ease or difficulty of measuring the breach in damages, and the amount of the stipulated sum, not only as compared with the value of the subject of the contract, but in proportion to the probable consequences of the breach, and also to the intent of the parties ascertained from the instrument itself in the light of the particular facts surrounding the making and execution of the contract.” Jones v. Stevens (1925), 112 Ohio St. 43, 146 N.E. 894, paragraph one of the syllabus. “Neither the parties’ actual intention as to its validity nor their characterization of the term as one for liquidated damages or a penalty is significant in determining whether the term is valid.” 3 Restatement of Contracts, supra, at 159, Section 356, Comment c. See Samson Sales, Inc. v. Honeywell, Inc. (1984), 12 Ohio St.3d 27, 28, 12 OBR 23, 24, 465 N.E.2d 392, 394. Thus, when a stipulated damages provision is challenged, the court must step back and examine it in light of what the parties knew at the time the contract was formed and in light of an estimate of the actual damages caused by the breach. If the provision was reasonable at the time of formation and it bears a reasonable (not necessarily exact) relation to actual damages, the provision will be enforced. See 3 Restatement of Contracts, supra, at 157, Section 356(1).
B
The test developed in Ohio to judge a stipulated damages provision was set forth in Samson Sales, Inc. v. Honeywell, Inc., supra:
“Where the parties have agreed on the amount of damages, ascertained by estimation and adjustment, and have expressed this agreement in clear and unambiguous terms, the amount so fixed should be treated as liquidated damages and not as a penalty, if the damages would be (1) uncertain as to amount and difficult of proof, and if (2) the contract as a whole is not so manifestly unconscionable, unreasonable, and disproportionate in amount as to justify the conclusion that it does not express the true intention of the parties, and if (3) the contract is consistent with the conclusion that it was the intention of the parties that damages in the amount stated should follow the breach thereof.” Id. at paragraph one of the syllabus, citing Jones v. Stevens, supra, paragraph two of the syllabus.
Using this test, we conclude that the damages in this case are liquidated damages.
First, when Carney and Lake Ridge entered into their contract in March 1989, the damages that Lake Ridge might suffer as a result of a breach by Carney were “uncertain as to amount and difficult of proof.” As the court of appeals explained, Lake Ridge goes through a long budgeting process which begins each year in January and ends in the fall. The tuition money paid by