structed and ruled that third party interests were not prejudiced.
On appeal, appellants argued the trial court erred in not holding (1) their nonliability for the extra materials; (2) the invalidity of the lien on several grounds; (3) appellants were entitled to a jury trial; and (4) liability of respondent for the $1,225 wages paid to the laborers.
There was a decided conflict in the evidence concerning the liability for the extra materials. Appellants asserted McFerran was not their agent, or if he was, he acted outside the scope of his authority in ordering extra materials; at least, those used in connection with the paint shop.
As appellants argued, the rule is that agency cannot be proven by declarations of the alleged agent. See, Ford v. United Brotherhood of Carpenters & Joiners of America, 50 Wn.2d 832, 315 P.2d 299 (1957). Other evidence, however, substantiated the trial court’s finding that McFerran was general agent to oversee the construction of the ice arena. Buchanan visited the building site on several occasions and knew what McFerran was doing. He made no complaint about his actions.
As to the extra materials, the court found in findings of fact No. 6, that “All of these materials were ordered by McFerron, were, in fact, installed in the building and were reasonably necessary to the completion of the building for its intended use as an ice arena.” The evidence sustained this finding.
As to those materials used in construction of the paint shop, the court found
[T]hat this extra work was specifically ordered by Mr. McFerron and though Buchanan may have understood that it was being done for McFerrons own benefit it clearly was not so understood by Geffe or the plaintiff [Lumber Mart] and it is again clear that the plaintiff [Lumber Mart] supplied the additional materials for the storage area at McFerrons request with no knowledge of any lack of his authority to order the additional work or materials. Finding of fact No. 8.
Appellants argued that respondent failed to