could be remedied without impairing the physical structure of the buildihg was not submitted to the jury.
Hutson objected to the submission of Special Issues Nos. 1, 2 and 3, in answer to which the jury found that the defects in workmanship could be remedied without impairing the building as a whole at a reasonable cost of $6,000. One objection thereto was that they submitted an incorrect measure of damages; that the correct measure of damages would be the difference, if any, in valúe of the building as .constructed and its value had it been constructed according to contract. He does not bring that question here in that precise form, but his first point is that it was error to submit the case on three theories. Under that point it is argued that the charge should have submitted special issues on only one theory of recovery, namely, the difference in value, if any, between the building as constructed and its value had it been constructed according to contract. We have concluded that the point and the argument thereunder present the question of whether the court should have submitted any special issues on the cost of remedying defects or deviations. It seems clear that under the pleadings of Chambless there was one, and only one, correct measure of damages.
To remedy the alleged defects and deviations according to the pleadings of Chambless would require not only the expenditure of a large sum of money, but the rebuilding of the foundation, the tearing down of the brick veneer and rebuilding it with better materials, the rebuilding of the den at a cost of more than $3,000, and removing and replacing the tile in the bathroom, to mention some of the alleged requirements. It is not claimed that Hut-son intentionally deviated from -the contract. On the contrary, it was alleged that it was through inadvertence. Under these facts, the rule for measuring the damages is well settled. It is stated by the Supreme Court of Washington in White v. Mitchell, 123 Wash. 630, 213 P. 10, 13, in this language :
“Where it is necessary, in order to make the building comply with the contract, that the structure, in whole or in material part, must be changed, or there will be damage to parts of the building, or the expense of such repair will be great, then it cannot be said that there has been a substantial performance of the contract. Generally, where there has not been such substantial performance, the measure of the owner’s damage is the difference between the value of the building as constructed and its value had it been constructed' in accordance with the contract. Such a recovery would be just to both'parties. It.is manifest that to measure the owner’s damage by the cost necessary to make the building conform to the contract would often be an injustice, because in many instances such cost would amount to almost as much as the original contract price.”
That rule was followed in Totten v. Houghton, Tex.Civ.App., 2 S.W.2d 530, no writ history, and authorities therein cited. It is announced in practically the same language in 9 American Jurisprudence, Building and Construction Contracts, Sec. 43, p. 33. Many authorities supporting the rule are annotated in 23 A.L.R. 1436, 38 A.L.R. 1383, and 65 A.L.R. 1298.
It is claimed that, since there were findings by the jury that the house was worth $7,100 less than it would have been worth had it been constructed according to contract, judgment could have been rendered in favor of Chambless for $7,100, and that Hutson cannot complain that judgment was rendered against him for $6,000 instead of $7,100. That contention might be sustained if the issues submitting the question of value had been properly framed. This brings us to a consideration of Hut-son’s objections to those issues. The issues and answers thereto were: