Opinion for the Court filed by Chief Judge MTKVA.
Opinion dissenting in part filed by Circuit Judge WALD.
MIKVA, Chief Judge:
TDC Management Corporation (“TDC”) entered into a cost-reimbursement contract with a federal agency to implement a Demonstration Bonding Program pairing minority business enterprises with private investors. When the Program failed to progress as expected, the agency terminated it for convenience and disallowed $441,972 of the $928,-916 TDC claimed as contract-related expenditures. Appellees, TDC Management Corporation and its President, appealed these cost disallowances to the Department of Transportation Board of Contract Appeals (“DOTBCA” or “Board”). Before DOTBCA rendered its verdict, the United States brought suit in district court alleging that TDC violated the False Claims Act by misrepresenting in monthly reports its actual progress implementing the Program.
The Board held that appellees were entitled to cost-reimbursements in all cost categories that the agency sought to disallow and that appellees had not breached the contract for nonperformance. Based on the collateral estoppel effect of the Board’s findings, appel-lees moved for summary judgment in district court on the government’s False Claims Act claim. The district court granted TDC’s motion. We now affirm in part and reverse in part.
I. Background
TDC Management Corporation contracted with the Urban Mass Transportation Administration (“UMTA”), an instrumentality of the Department of Transportation, to implement and administer a Program assisting minority business enterprises (“MBEs”) in securing bonding from sureties when bidding on large transportation construction projects. Specifically, TDC agreed to seek out private investors willing to contribute management assistance and up to $3 million in collateral to the MBEs in return for a percentage of the profits on construction projects. UMTA was to match the collateral that investors contributed. By the terms of the Program, TDC was to serve as an ombudsperson between the parties, with no financial interest in Program operations.
Pursuant to its contract with UMTA, TDC submitted monthly progress and expenditure reports to UMTA. UMTA reimbursed TDC monthly for documented expenditures. The government claims that TDC’s reports overstated its progress in attracting investors and failed to disclose that, contrary to the Program design, TDC sought to obtain a financial interest in Program operations. The government claims that UMTA would not have made payments to TDC had it been aware of either of these facts.
UMTA first learned of TDC’s alleged misrepresentations in December 1984. On April 5, 1985, it issued a termination for convenience. UMTA had, to that point, paid TDC $747,944 for contract-related expenditures. On June 1, 1985, TDC submitted a termination settlement proposal seeking an additional $216,133 in contract reimbursements. In May 1986, a UMTA contracting officer held that only $486,944 of the total $928,916 claimed by TDC over the life of the contract were “allowable, allocable, and reasonable.” The officer categorically disallowed TDC’s undocumented travel costs, computer costs, excessive per diem charges, cost overruns, and costs associated with TDC’s Los Angeles office. The officer requested that TDC reimburse UMTA for the $261,615 overpayment that TDC had already received.
TDC appealed the contracting officer’s decision to DOTBCA, claiming that it was entitled to an additional $143,852 in cost-reimbursements from UMTA plus $9,830 in termination costs. UMTA raised three affirmative defenses to TDC’s claims: (1) TDC failed to perform the tasks in the contract statement of work; (2) TDC obtained the contract “by fraud and misrepresentation”; and (3) TDC “perpetrated frauds ... in presenting vouchers for payment of costs claimed” under the contract. UMTA also filed a counterclaim, grounded in restitution and breach of contract, seeking recovery of all contract payments already made to TDC.