On September 28, 2001, ECO accepted the building as substantially complete, submitting an eight-page punch list of items in need of repair to TASL. About this same time, ECO received formal notice of the property’s pending sale in a document entitled “Notice of Assignment of Lease and Estoppel Certificate.” ECO promptly executed the estoppel certificate, as its lease required,1 and returned it a mere twelve days after submitting its punch list to TASL. Two weeks later, Ashford became ECO’s landlord. Four days after that, the deadline for completing ECO’s punch list expired. At least one repair on the punch list, a requirement for caulking between the tilt wall panels under grade, had not been performed.
Two years passed, and ECO began to have problems with the building. Ashford hired engineers to investigate, and they determined that water had collected under the foundation. The cause for this was traced to the failure to caulk between the tilt wall panels below grade, the omitted repair on ECO’s punch list.
Ashford spent over $313,000 to make repairs and correct the problem and then sued the construction contractor that TASL had used on the project. Ashford also joined ECO as a defendant, seeking a declaratory judgment that the building was structurally sound and that ECO was not entitled a reduction in rent. ECO counterclaimed for breach of the lease, asserting that Ashford as successor landlord assumed the original lessor’s obligations under the lease, including the duty to construct the building according to plans.
Ashford subsequently settled with the construction contractor and also dismissed its suit against ECO. ECO did not abandon its claim, however, and the case proceeded to trial. At this trial, a jury was asked the following three questions:
• Did Ashford fail to comply with the Lease by failing to cause the Leased Space to be constructed pursuant to the Plans?
• Did Ashford fail to comply with the Lease by failing to maintain the foundation of the Leased Space in good repair?
• What sum of money, if any, if paid now in cash would fairly and reasonably compensate ECO Resources for the damages, if any, that resulted from Ash-ford’s failure to comply with the Lease?
The jury answered ‘Tes” to the first question and “No” to the second, finding Ash-ford had breached a construction-related duty under the lease but not its duty to maintain the foundation in good repair.2
In the third question on damages, the jury was instructed to base its award, if any, on the difference “between the rent required under the Lease and the rental value of the Leased Space in its actual condition.” The jury found the diminished value of the lease to be $1,027,704. Adding interest and attorney’s fees,3 the trial court rendered a total judgment of $1,494,462.25 in favor of ECO. Ashford appealed.
The court of appeals concluded that Ashford had assumed a duty to oversee
1
The lease required ECO to execute an estop-pel certificate, verifying the lease’s validity and other matters, within ten days of the landlord’s request.
2
The lease obligated the landlord to keep the building’s foundation, walls, and roof in good repair.
3
.The parties stipulated to $407,046.20 as a reasonable and necessary attorney’s fee in this case.